by no-name-here 85 days ago
It typically takes 11-12 years for a nuclear plant to get built including planning and construction [1].

Is the idea that we'd build the data centers now, and finish the nuclear plants to power them 11-12 years from now?

https://www.researchgate.net/figure/Typical-timeline-of-a-nu...

1 comments

For wind turbine project from design and planning to operational use-takes approximately 4-7 years. An offshore wind turbine project requires about 7-10 years.

https://jmhpower.com/how-long-does-it-take-to-build-a-wind-t...

> For wind turbine project from design and planning to operational use-takes approximately 4-7 years.

That's still better than 11-12 years. How long does a solar farm take?

If residents' opposition is rooted in higher power prices, data centers could just pay extra instead until the new capacity comes online. Seems like a cheap way to pay off opposition.

> An offshore wind turbine project requires about 7-10 years.

Given this article is about Pennsylvania, it'll probably take millions of years.

> How long does a solar farm take?

24–48 months, but for a data center that has to run 24/7 you need to also build a gas power plant.

https://www.pvfarm.io/blog/utility-scale-solar-project-devel...

https://globalenergymonitor.org/research/betting-big-data-ce...

Or use batteries.

Also residential and industrial use will be lower at night. So the existing grid supply may also be enough.

In many places the contraty is true, peak electricity prices are after sunset, during night.
> peak electricity prices are after sunset

The famous evening duck curve, when people go home and cook and turn on heating/cooling appliances. California is able to flatten that out with batteries alone.

https://eticaag.com/battery-storage-and-the-duck-curve-march...

> during night

When everyone's asleep? Serious doubt, please show your sources.

Adding to the sibling comment, from your link:

* The longest piece for wind is "Approvals and permits" which takes up to 5 years of the 4-7y.

* The building part "takes approximately 3-6 months" for building wind.

So wind can be built far faster if we're willing to speed up approvals and permitting. And even if corners are cut for approvals/permitting, the worst case for a wind turbine failure is a lot better than a nuclear failure.