This is my heuristic for the capex split and effective lifetime of the asset it creates (I'm no expert of course, this is based on various reading): - 20% Capex has ~20-year lifetime: The shell (land, building, cooling gear, rack mounts, power lines etc.). - 80% Capex has ~3-year lifetime: The computers, including bulk commitments to power and maintain them. And interest rates are why this split is a ticking time bomb. The sheer quantum of investment to build one is almost entirely debt funded (~90% of total outlay). I would guess the endgame would be bad even if the split for these entirely different asset classes is 50/50, which would be very generous, based on what I've understood. Datacenter funding is extremely leveraged. For comparison, only some banks are allowed that much leverage for that size of capital, that too only if they have federal reserve backing. Even in such a case, the retail account holder (pseudo-investor, because our deposits are loans to someone else) has practically no downside protection. If the bank collapses you will lose everything. |
In fact, to focus on the short lifetime assets alone, this more recent link suggests servers are 50% of CapEx, and GPUs are about 25 percentage points.
https://cib.bnpparibas/ai-infrastructure-investment-2026/
So already about 50% of CapEx spend is one-off construction / installation with a very long lifetime.
That leaves servers and GPUs. There is a ton of evidence out there that even chips from multiple generations ago, ie way more than 3 years old, are commanding pretty high rates. So even if they are replaced by newer chips every year, the older chips still hold a lot of value and can’t simply be written off to 0.
I think this is the most comprehensive look at the AI economy so far, probably a better source than the rest: https://www.exponentialview.co/p/the-state-of-the-ai-economy — it suggests everything is walking a tightrope but still sustainable for now.